Power generation slides to 4245MW

By Sulaimon Salau
23 February 2016   |   1:59 am
Hopes of having a stable power supply in the country may have become elusive as more power stations and sub-units remain inactive, bringing the generation level down to 4245 Mega Watts (MW).
Olorunsogo Power Plant

Olorunsogo Power Plant

. Stranded energy hits 2146MW, group protests electricity tariff increase
Hopes of having a stable power supply in the country may have become elusive as more power stations and sub-units remain inactive, bringing the generation level down to 4245 Mega Watts (MW).

The nation recorded the peak generation of 5074MW on the 2nd of February, but the daily operational report, including the national statistics on generation profile exclusively obtained by The Guardian yesterday indicated that about 20 power stations are operational out of the 25 power facilities in the country.

The Olorunsogo power station operated under the National Independent Power Projects (NIPP) was also reportedly shut down due to gas constraint and maintenance programme, reducing power generation by 600MW.

Besides, some of the 20 operational plants also have some units shut due to gas limitations, water shortage, transmission constraints and maintenance. This has however brought the unutilised generation capability to 2146.5MW.

However, the peak national demand, according to the report stood at 14,630MW.

No fewer than seven power plants were affected by gas constraints. These are Olorunshogo NIPP GT1-4 and ST2 units (600MW); Sapele NIPP GT 3&4 (225MW); Omotosho GT2-4 and 6 (152MW); Geregu NIPP GT21 and 23 (290MW); Delta GT9, 10, 11, 18 and 19 (260MW); Olorunsogo GT2-4 and 8 units (152MW); and Ihovbor GT4 (112.5MW).

It noted that “it is envisaged that with improved plant availability and relief from existing power system network related constraints, additional 1637.17 million standard cubic feet of gas (equivalent to 6139.4MW) will bé required when all thermal units are on bar,”

One power plant is impacted by water management – Jebba 2G2 (85MW), while two plants are affected by transmission line constraints, these are Odukpani GT5 (120MW) and AfamV1 GT11 (150MW).

As at yesterday, five out of six units in Egbin power plant were on stream, while unit ST1was out due to generator circuit breaker trouble.

Meanwhile, the Consumer Rights Advancement Organisation (CRADO) said it is “highly unlawful and a flagrant abuse of consumer rights, for electricity consumers to pay the new tariff before getting the meters,”

President, CRADO, Adeolu Ogunbanjo, in a statement made available to The Guardian, said: “Why should electricity tariff increase when the extant law for such increment was not followed in consonance with section 76 of the Power Sector Reform Act, 2005.

0 Comments

  • Author’s gravatar

    Back to 1998. Power has made a lot of millionaires but still Nigeria lack power

  • Author’s gravatar

    Gas supply problem. yet we are exporting the gas we have, we are flaring gas and there is no investment in gas supply or exploration by the government. Instead of wasting money on international trips and useless project, why doesn’t the government invest in more gas exploration and supply. why hasn’t the government mandated a larger percentage of gas go to domestic use. yet the minister and NERC want the people to continue to pay estimate billing with higher traffic for no electricity and no meter. This country is being led by criminals.